[Termination on an Authority Break Point Date

42.2  Without prejudice to its rights under Clause 42.1, the Authority may terminate this Agreement on any of the Authority Break Point Dates by complying with its obligations under Clause 42.2.1 below.

42.2.1  If the Authority wishes to terminate this Agreement under this Clause it must give notice to Project Co stating:

(a)  that the Authority is terminating this Agreement under this Clause 42.2; and

(b)  that this Agreement will terminate on the specified Authority Break Point Date, which must be a minimum of [30] days after the date of receipt of the notice.

42.2.2  Provided the notice has been provided in accordance with Clause 42.2.1 above, this Agreement will terminate on the specified Authority Break Point Date.]