13  Project Documentation

13.1  Unless the parties otherwise agree, no changes to the Project Documents shall be made as a result of a Medium Value Change.

13.2  Project Co shall, no later than one (1) month following completion of a Medium Value Change, update the as-built drawings and the operating and maintenance manuals as necessary to reflect the Medium Value Change.