1  High Value Changes

1.1  If the Authority requires a High Value Change it must serve an Authority Change Notice on Project Co in accordance with paragraph 2 of this Section 4 (High Value Changes).  

1.2  Project Co shall be entitled to refuse a High Value Change that:

1.2.1  requires the Works and/or the Services to be performed in a way that infringes any law or is inconsistent with Good Industry Practice;

1.2.2  would cause any Necessary Consent to be revoked (or would require a new consent to be obtained to implement the relevant change in the Works and/or the Services which, after using reasonable efforts, Project Co has been unable to obtain);

1.2.3  would materially and adversely affect Project Co's ability to deliver the Works and/or the Services (except those Works and/or Services which have been specified as requiring to be amended in the High Value Change Notice) in a manner not compensated pursuant to this Section 4 (High Value Changes);

1.2.4  would materially and adversely affect the health and safety of any person;

1.2.5  would, if implemented, materially and adversely change the nature of the Project (including its risk profile); 

1.2.6  is the subject of a High Value Change Notice that cannot reasonably be complied with; 

1.2.7  the Authority does not have the legal power or capacity to require implementation of; or

1.2.8  would if implemented adversely affect the enforceability or priority of the security held by or on behalf of the existing Senior Lenders.