11) In your opinion and based on the outcomes of your PPP project(s), was there some information that you did not have, but that could have been beneficial in the decision-making process?

Of 15 responses:

Yes 

6
40%

 

No


60%

If you answered "yes," please explain:

•  Costs/value of transferred risk

•  Private investor's internal rate of return calculations

•  No PPP projects completed. Knowledge of future would be helpful.

•  Best practices or case studies would be beneficial

•  Current toll PPPs are in development stages.

•  More detailed Traffic and Revenue at onset of proposal review