5) What criteria are used to decide whether a PPP approach should be used for project delivery in your agency?
| Total | Extremely | Somewhat | Not | N/A |
Project is an urgent transportation need | 26 | 15 | 6 | 1 2.3% | 4 |
Strong political, public, and institutional support | 27 | 16 | 6 | - | 5 |
Project acceleration potential | 27 | 15 | 7 | - | 5 |
Project could generate sufficient revenues to attract private investment | 27 | 14 | 6 | - | 7 |
Lack of traditional funding | 26 | 17 | 4 | - | 5 |
High-risk project that could be better managed by private sector | 26 | 7 | 9 | 5 | 5 |
27 | 1 | 5 | 10 | 11 | |
Other (specify below): | 12 | 1 | - | - | 11 |
Percentage indicates proportion of total surveys, including those that returned no response to Q5.
• All items will be important if/when PPP proposals become active
• [State] does not routinely use PPPs.
• These are the considerations that we have used in trying to get legislation passed.