9) The table below lists various tools that may be used to select a private partner. Please indicate the degree to which your agency uses any of these tools when considering a PPP proposal.

 

Use
Frequently

Use
Sometimes

Use
Rarely

N/A (do not
use)

Benefit-cost analyses


40%


40%

-


20%

Internal Rate of Return/Net Present Value analyses


40%


20%

-


40%

Value-for-Money/Public Sector comparators


40%

1
20%


20%


20%

Traffic and Revenue Studies

-


20%


20%


60%

Risk assessment


20%


40%


20%


20%

Availability Payment Amount/Net Present Value


60%

-


20%


20%

Independent evaluation from legal and/or financial consultants


20%


40%


20%


20%

Other (specify below):

-

-

-

-

No responses.

The next two questions pertain to information used in making decisions about PPPs. If your agency has not yet seriously assessed possibilities for any highway-related PPPs, please click "Next Page " at the bottom of the screen and skip ahead to Question #12