16.10.1 If the Authority does retain some control over sub-contractors and/or employees then the Contract should contain a procedure to be followed to confirm whether the Authority has any objections to a particular party. Any failure by the Authority to respond within the specified time limit should be dealt with in accordance with Section 5.2 (Compensation Events). Authorities should consider carefully whether their "approval" can be deemed to be given if they fail to respond.