20.5  TRANSFER OF RESIDUAL VALUE RISK

20.5.1  Where there is the potential for alternative use, and hence alternative users, of the Service or any Assets, there may be scope for the Contract to include provisions that transfer some residual value risk to the Contractor.276 It is crucial that this issue is dealt with as part of the competitive bidding process if it is to deliver real value.

20.5.2  There are a number of issues for an Authority to consider. First, is it likely to require long-term use of the Assets? If so, it is unlikely to derive best value from transferring residual value risk. Second, if the Authority has no clear long-term requirement for the Assets, is it possible for the Authority to pass on any residual value risk to the Contractor? Third, will transfer of residual value risk provide value for money? Finally, how will transfer of residual value impact on any payment on termination on expiry of the Contract.

20.5.3  It will not be possible in all cases to leave the residual value risk of the Assets with the Contractor, even if there is some potential for alternative use. The difficulty of estimating value and the required length of the initial Contract may make it uneconomic for the Contractor to estimate the residual value of the Asset at anything other than an insignificant amount. In such circumstances, financiers277 are unlikely to accept being exposed to significant residual value risk. It will in such circumstances generally not represent value for money for the Authority to transfer this risk as the Contractor will expect to obtain its return over the life of the Contract.

20.5.4  If transfer of residual value risk will enhance value for money, the Authority can pay a Unitary Charge which does not enable the Contractor to cover the complete cost of financing its investment through the service payments it receives during the Contract. The Contractor instead has to rely on value being left in the Assets remaining on the Expiry Date to recover all such cost. This leaves some real risk with the Contractor in relation to the residual value at the end of the Contract. Where this is the case it will be possible to have a shorter Contract length (see Section 2 (Duration of Contract)). When residual value is to be transferred, an appropriate leasehold (or freehold) structure should be used and the definition of Assets amended accordingly. Authorities should also consider Residual Value Risk when setting any capital expenditure contribution limits or liabilities (for example on a Qualifying Change of Law - see Sections 14.6 to 14.8).

20.5.5  The options exercisable by the Authority on the Expiry Date in relation to Assets with an alternative use where the Contractor is taking the residual value risk are:

•  to take over the Asset, in which case a payment should be made to the Contractor (see Section 20.6 (Valuation of Terminal Payments on Expiry where Residual Value Risk has been Transferred));

•  to re-tender the Service, in which case the successful Contractor in the re-tendering exercise should make a payment to the previous Contractor reflecting the value of the Assets (see Section 20.6 (Valuation of Terminal Payments on Expiry where Residual Value Risk has been Transferred)); or

•  if the Authority has no further use for the Assets, to walk away at no further cost, leaving the Contractor to realise their value.

20.5.6  Each of these options affords the Contractor the ability to realise the value of the Assets upon expiry of the Contract, and accordingly the NPV of the total Unitary Charges payable under the Contract should be lower than if the Residual Value Risk had been retained (subject, of course, to there having been a well run competition).

20.5.7  Suitable drafting (where Residual Value Risk has been transferred) is as follows:

20.5  Assets with an Alternative Use

(a)  On or before the date falling [six] months278 before the Expiry Date, the Authority shall notify the Contractor in writing whether it wishes to:279

(i)  purchase the Assets by paying to the Contractor an amount equal to the Terminal Payment;

(ii)  retender the provision of the Service;280 or

(iii)  do neither (i) nor (ii) above.

(b)  If no notice is given under paragraph (a) above, then the Authority shall be deemed to have exercised its option under paragraph (a)(iii) and the Assets shall remain with the Contractor.

(c)  If the Authority wishes to exercise its option under paragraph (a)(i) above, then:

(i)  the Contractor and the Authority shall do all necessary acts (including entering into any contracts) to ensure that on the Expiry Date, the Assets are transferred to the Authority;

(ii)  Within [30] days of effective transfer of ownership of the Assets to the Authority, the Authority shall pay to the Contractor the Terminal Payment.281

(d)  If the Authority wishes to exercise its option under paragraph (a)(ii) above, then:282

(i)  it shall carry out the retendering with the aim of entering into a new contract with a successor contractor to provide the Service on and from the Expiry Date;283

(ii)  a condition of any retendering shall be that the successor contractor must pay the Contractor the Terminal Payment on transfer of ownership of the Assets to the successor contractor; and

(iii)  the Contractor and the Authority shall do all necessary acts (including entering into any Contracts) to ensure that ownership of the Assets is transferred to the successor contractor with effect on and from the Expiry Date.

20.5.8  The Contract will also need to take account of Assets retained by the Contractor in the various scenarios where the Contact may be terminated prior to its expiry date. See Section 22.6 (Retention of Assets by Contractor on Termination).




___________________________________________________________________________

276  See for instance the social housing sector and see Section 19.3.

277  Senior Debt is usually profiled to be repaid in advance of the Expiry Date. This may not however be the case on a corporately financed housing project.

278  The precise wording will depend on the specific circumstances. This wording assumes that effective ownership of the Assets is already with the Contractor and that, if the Authority wishes to continue to use the Assets, the Authority will need to make a payment or hold a new tender competition. If the Authority already owns part or all of the Asset (or will do so at the end of the Contract) these provisions would need amending accordingly.

279  Any relevant procurement implications should be taken into account. To the extent option (a)(ii) is likely, the process may have to start earlier.

280  The Authority will also need an option to purchase the Assets to allow any new Contractor to provide the Service.

281  This Clause should not be used and no payment should be made by the Authority if the Contractor did not accept any residual value risk during the term of the Contract so that the Authority paid a Unitary Charge which was capable of providing the Contractor with sufficient funds to fully amortise its capital debt and equity in accordance with its base case financial model. The meaning of "Terminal Payment" is explained in Section 20.6.1.

282  If the incumbent Contractor wins a retender then it should still be entitled to receive a Terminal Payment, reflecting the market value of the Assets unless such value has been included within the incumbent Contractor's tender price.

283  Any retendering would have to follow any applicable procurement rules.