| SoPC Section (or Clause) | Nature of Revision | Description of Revision | Drafting Change (shown in bold) |
| 5.2 (Clause) Delays | New small change to Required Drafting |
| (c) In the event that the Contractor has complied with its obligations under paragraph (b) above, then: (i) in the case of a delay, the Planned Service Commencement Date or, following the Planned Service Commencement Date, the Long Stop Date, shall be postponed by such time as shall be reasonable for such a Compensation Event, taking into account the likely effect of delay; |