Tasks relevant to construction

•  Report as required by governance structure on progress of the project and highlight any issues or risks and update the risk register;

•  Check and organise technical advisers to help check Reviewable Design Data (RDD);

•  Supervise and manage the RDD process on behalf of the Authority;

•  Monitor the detailed design progress through the scrutiny of drawings and attendance at Contractor's design meetings;

•  Ensure design issues are identified and dealt with at early stages;

•  Continue to ensure and arrange stakeholder involvement;

•  If there is a requirement for change, manage the Authority Change Order process, raising Authority Notices of Change (ANCs) where necessary  obtaining specialist help for checking assessments of cost put forward by the Contractor;

•  Negotiate with the Contractor on areas in Contractor's Proposals/Authority Requirements which are not completely clear.  (NB: as detailed design is developed there are likely to be grey areas which the Contractor may have a different view to the Authority on what should be provided.);

•  Attendance at Contractor's progress meetings, RDD meetings, ANC meetings, sign off meetings;

•  Manage Authority involvement in snagging inspections and monitor Independent Certifier reports;

•  Manage and resolve information and change requests from the Contractor;

•  Monitor Contractor progress and ensure action is taken if there are any delays to ensure availability on time;

•  Monitor and record all written and email communication between the Authority's project and contract management team and Contractor's team;

•  Ensure Health & Safety and Operation & Maintenance manuals are progressing appropriately and info is being passed as necessary to the FM sub-contractor. (NB: This is a Contractor obligation but it is best practice to monitor this); 

•  Liaise and organise client involvement in any publicity or other events agreed as part of the Communication Plan; and

•  Ensure all documents and correspondence are lodged and clearly referenced/filed in the project's Data Room, and the information is continuously updated in line with the project's development.