Increased monitoring

18.2  If, following any viewing, visit or inspection made pursuant to Clause 18.1(a) (Access to Site), it is discovered that there are defects in the Works or that Project Co has failed to comply with the Board's Construction Requirements or Project Co's Proposals, the Board's Representative may (without prejudice to any other right or remedy available to the Board) by notice to Project Co increase the level of monitoring of Project Co until such time as Project Co shall have demonstrated to the satisfaction of the Board that it is capable of performing and will perform all its obligations to the Board under this Agreement.  Project Co shall compensate the Board for any reasonable additional costs incurred as a result of such increased monitoring.