The Programme

19.2  Any Programme submitted in accordance with the provisions set out below shall be prepared in accordance with Good Industry Practice and shall be in sufficient detail so as to enable the Board's Representative to monitor the progress including all commissioning activities and likely future progress of the Works.

19.3  The initial Programme is set out at Part 9 of the Schedule (The Programme).  Any change to the Programme shall only be made in accordance with this Clause 19 and Part 10 of the Schedule (Review Procedure).  Project Co shall promptly submit to the Board's Representative a copy of any version of the Programme varied in accordance with this Clause 19 and Part 10 of the Schedule (Review Procedure).

19.4  If it appears to the Board's Representative at any time that the actual progress of the Works has significantly fallen behind the Programme, then the Board's Representative shall be entitled to require Project Co to submit to the Board's Representative a report identifying the reasons for the delay and, unless the event causing the delay is still subsisting and it is not possible to predict with any certainty when the delay might come to an end, require Project Co (at the Board's option):

(a)  to produce and submit to the Board's Representative in accordance with Part 10 of the Schedule (Review Procedure) a revised Programme showing the manner and the periods in which the Works will be carried out to ensure completion; and/or

(b)  to produce and submit to the Board's Representative in accordance with Part 10 of the Schedule (Review Procedure) a revised Programme showing the steps which are to be taken to eliminate or reduce the delay.