47 The standard form envisages the following sequence of events:
• Final Commissioning Programme ("FCP") agreed
• Project Co commissioning needed in order to achieve Practical Completion
• Board to carry out its commissioning activities scheduled to take place prior to completion (if any)
• Project Co to carry out completion tests in accordance with FCP
• Visual inspection by Board and Independent Tester
• Certificate of Practical Completion and snagging list issued
• Commencement of appropriate percentage of the unitary charge see Clause 35.1
• Project Co post completion commissioning activities in accordance with FCP
• Board post completion commissioning (including, for example, installation of its equipment and decant to new site) in accordance with FCP.