22.  PRE-COMPLETION COMMISSIONING AND COMPLETION47

 










_______________________________________________________________
47 The standard form envisages the following sequence of events:

•  Final Commissioning Programme ("FCP") agreed

•  Project Co commissioning needed in order to achieve Practical Completion

•  Board to carry out its commissioning activities scheduled to take place prior to completion (if any)

•  Project Co to carry out completion tests in accordance with FCP

•  Visual inspection by Board and Independent Tester

•  Certificate of Practical Completion and snagging list issued

•  Commencement of appropriate percentage of the unitary charge   see Clause 35.1

•  Project Co post completion commissioning activities in accordance with FCP

•  Board post completion commissioning (including, for example, installation of its equipment and decant to new site) in accordance with FCP.