Project Co Services Changes

27.3  Project Co may at any time submit to the Board's Representative in accordance with Part 10 of the Schedule (Review Procedure) proposals for amendments to or substitution for the Method Statements [or the Interim Service Statement] or any part of them. If there is no comment on such proposed amendment or substitution (on the grounds set out in paragraph 3(g) of Part 10 of the Schedule (Review Procedure)), then the Method Statements [or Interim Service Statements] as so amended or substituted shall be the Method Statements [or Interim Service Statements] for the purposes of this Agreement, subject to any further amendment or substitution to which there has been no comment in accordance with Part 10 of the Schedule (Review Procedure).

27.4  To avoid doubt, an amendment to or substitution for the Method Statements [or Interim Service Statements] proposed pursuant to Clause 27.3 shall not be a Qualifying Variation entitling Project Co to any payment (or other compensation) or to any relief from the performance of its obligations under this Agreement.