5 Year Maintenance Plan72

28.11  Project Co shall deliver to the Board's Representative not less than [                    ] Business Days prior to the commencement of each Contract Year the latest version of the 5 Year Maintenance Plan for the [indicate the relevant facilities service].

28.12  The Board shall have a right to inspect the Facilities and the Maintenance Works to ensure that the Facilities are being maintained in accordance with the Service Level Specifications and that the Facilities comply with the Board's Construction Requirements and Project Co's Proposals throughout the Project Term.  The Board may appoint an independent third party for the purposes of carrying out any such inspection and shall make known the findings to Project Co and the Funders.  The parties shall then meet to discuss any implications of such findings and any steps that are necessary to remedy any failure to comply with such obligations.  Project Co shall (subject to Clause 40 (Variation Procedure)) take into account such discussions in the next Schedule of Programmed Maintenance so that any failure to comply with such obligations shall be remedied.  

 




______________________________________________________________
72 The need for and the terms of a 5 year maintenance plan should be assessed on a project specific basis.