Default

(c)  

(i)  Project Co committing a material breach of its obligations under this Agreement which has a material and adverse effect on the delivery of Clinical Services or any other services140 at the [Hospital] for which Project Co is not responsible (other than as a consequence of a breach by the Board of its obligations under this Agreement);

(ii)  Project Co wilfully breaches Part 29 of the Schedule (Refinancing);  

(d)  Project Co abandoning the Works (other than as a consequence of a breach by the Board of its obligations under this Agreement);

(e)  Project Co ceasing to provide all or a substantial part of the Services to the Board in accordance with this Agreement (other than as a consequence of a breach by the Board of its obligations under this Agreement);

 




_________________________________________________________________
140 Boards to consider which "other services" are material to its ability to provide the Clinical Services.  Consider listing specified services.