44.3 On the occurrence of a Project Co Event of Default, or within a reasonable time after the Board becomes aware of the same, and while the same is subsisting, the Board may:143
(a) in the case of the Project Co Events of Default referred to in Clauses 44.1(a), 44.1(b), 44.1(c)(ii), 44.1(f), 44.1(g), 44.1(h) or 44.1(j), terminate this Agreement in its entirety by notice in writing having immediate effect;
(b) in the case of any Project Co Event of Default referred to in Clause 44.1(c)(i), 44.1(d) and 44.1(e), serve notice of default on Project Co requiring Project Co at Project Co's option either:
(i) to remedy the Project Co Event of Default referred to in such notice of default (if the same is continuing) within twenty (20) Business Days of such notice of default; or
(ii) to put forward within twenty (20) Business Days of such notice of default a reasonable programme (set out, if appropriate, in stages) for remedying the Project Co Event of Default. The programme shall specify in reasonable detail the manner in, and the latest date by, which such Project Co Event of Default is proposed to be remedied (Project Co shall only have the option of putting forward a programme in accordance with this Clause 44.3(b)(ii) if it first notifies the Board within ten (10) Business Days of such notice of default that it proposes to do so); and
(c) in the case of any Project Co Event of Default referred to in Clause 44.1(i) (Service Failure Points), if Project Co is awarded [ ] or more further [Service Failure Points/Warning Notices] in the following [ ] month period, terminate this Agreement in its entirety by notice in writing having immediate effect.
__________________________________________________________________
143 Boards should note that any rights to terminate will be subject to the terms of the Senior Funders' Direct Agreement.