15.  INFORMATION

15.1  hubco shall not in any way be relieved from any obligation under this Agreement nor shall it be entitled to claim against the Participant on grounds that any information, whether obtained from the Participant or otherwise (including information made available by the Participant) is incorrect or insufficient and shall make its own enquiries as to the accuracy and adequacy of that information.

15.2  Save to the extent expressly provided in a Project Agreement

15.2.1  none of the Participants nor any of their respective agents, servants or advisers shall be liable to hubco (whether in contract, delict or otherwise and whether or not arising out of any negligence on the part of the Participants or any of their respective agents, servants or advisers) in respect of any inadequacy of any kind whatsoever in Works and Facilities Information

15.2.2  no Participant shall be deemed to have given any warranty or undertaking that  Works and Facilities Information represents all of the information in its possession or power relevant or material to any New Project; and

15.2.3  none of the Participants nor any of their respective agents, servants or advisers shall be liable to hubco, any Project Service Provider or any Supply Chain Member in respect of any failure (whether before or after execution of the relevant Project Agreement) to: 

(a)  disclose or make available to hubco, a Project Service Provider or any Supply Chain Member any information, documents or data; or

(b)  keep Works and Facilities Information up to date; or 

(c)  inform hubco, any Project Service Provider or any Supply Chain Member of any inaccuracy, error, omission, unfitness for purpose, defects or inadequacy in Works and Facilities Information.

15.3  hubco acknowledges and confirms, for itself, the Project Service Providers and Supply Chain Members that:

15.3.1  before execution of each Project Agreement, they shall have conducted their own analysis and review of the relevant Works and Facilities Information and as such shall be deemed to have satisfied themselves as to the accuracy, completeness and fitness for purpose of all such Works and Facilities Information upon which they place reliance; and

15.3.2  save to the extent expressly provided in a Project Agreement, they shall not be entitled to make any claim against any of the Participants or any of their respective agents, servants or advisers, whether in damages or for extensions of time or additional payments under the Project Agreement, on the grounds of any misunderstanding or misapprehension in respect of the relevant Works and Facilities Information or on the grounds that incorrect or insufficient information relating thereto or to any Site was given to it by any person whether or not in the employ of the Participants, nor shall they be relieved from any risks or obligations imposed on or undertaken by them under the Project Agreements on any such ground.