17.8 Without prejudice to the rights of a Project Agreement Counterparty under its Project Agreement, where a Project Service Provider for a DBFM Project has notified a Project Agreement Counterparty of a risk becoming an Uninsurable Risk pursuant to the provisions of the relevant Project Agreement, the Participants and hubco shall co-operate so as to ensure that a meeting of the TPB is held as soon as is reasonably practicable (and in any event within seven (7) Business Days of receipt by the Project Agreement Counterparty of such notice). At that meeting the TPB shall consider the situation and the parties will work together to use all their respective reasonable endeavours to obtain an agreed position from the TPB in relation to the risk becoming an Uninsurable Risk within twenty (20) Business Days of the Project Service Provider notifying the Project Agreement Counterparty as described above.