The Contract allows the Board to scrutinise the construction. If it believes that there may be defects in the Works, it can begin to monitor the Works more closely, with the Contractor paying the Board's additional costs. However, if the Board causes a delay to the Contractor's work through an unjustified inspection, this could constitute a Delay Event where the Contractor may receive compensation (see Paragraph 19).