The Contract recognises that certain actions of the Contractor may lead to a loss to the Board, which cannot be adequately compensated for through the application of deductions. For example, if the Contractor failed to clean up a spillage within the stipulated period, a performance deduction might be incurred. However, if the Contractor's failure also led to a visitor slipping and injuring himself, the cost of any resulting claim against the Board (and the Board's associated expenses) must be met by the Contractor. The Contract therefore contains an indemnity by the Contractor in favour of the Board for:-
30.1.1 Death and/or personal injury;
30.1.2 physical loss or damage to the Board Assets; and
30.1.3 Third party actions/claims.