Statutory Testing

PS Ref

Performance Standard

Performance Monitoring

Category

Response Period

Rectification Period

Monitoring Method

Performance Monitoring Period

Remedial Period / Remedy

Statutory Testing

FM64

Sub-hubco shall ensure that all statutory testing of equipment and systems is carried out by a competent operator in line with manufacturer's instructions within the agreed statutory or manufacturer's prescribed test period.

[Major]

N/A

N/A

Review of testing records and certificates.

Monthly

5 Business Days.
To commence at the start of 2nd Business Day following the end of the Contract Month.
Remedy: Complete all outstanding statutory testing by a competent person.