A risk premium will be included in the cost of risk transferred to private sector, effectively representing the value of the risk to the contractor.
Risks should be transferred when the cost of transfer is lower than the cost of the Procuring Authority retaining and mitigating the risk.
Cost of risk transfer includes the one-off cost of specifying the risk to a level suitable for inclusion in a legal contract.