13.7 Unavailability of Existing Facilities
If any area of the Existing Facilities (in the reasonable opinion of the Authority) cannot continue to be used for the provision of the [Authority/Community] Services prior to the Actual Completion Date [Phase Actual Completion Date] through a failure by [Sub-hubco/Project Co] to carry out the Works in accordance with Clause 12 (The Design, Construction and Commissioning Process) and Clause 14 (Programme), then at the option of the Authority, [Sub-hubco/Project Co] shall either:
13.7.1 reimburse to the Authority the proper costs reasonably incurred by the Authority in providing alternative accommodation and associated arrangements; or
13.7.2 provide at [Sub-hubco's/Project Co's] expense, equivalent alternative accommodation in a location with the town boundaries of where the Existing Facilities are situated and provide such additional or alternative ancillary services as may be required to enable that accommodation to be used for the provision of the [Authority/Community] Services.