Additional Hours

22.13 Subject to the Authority giving [Sub-hubco/Project Co] reasonable prior notice, having regard to the nature and extent of the use required, the Authority may require that:

22.13.1 any Functional Area be used by the Authority or for Community Use outside Core Times; or

22.13.2 any Functional Area in excess of the Functional Areas detailed in the definition of Core Times be used by the Authority or for Community Use during Core Times.

The Authority must reimburse [Sub-hubco/Project Co] for any additional costs and expenses (including overhead, administration costs and profit incurred by [Sub-hubco/Project Co] and any Service Provider, which all taken together must not exceed [%] of the direct costs of providing the Services), reasonably, properly and demonstrably incurred by [Sub-hubco/Project Co] as a result of the use by the Authority or the Community Use of that Functional Area, the additional use of which has been requested by the Authority in terms of this Clause 22.13.6



______________________________________________________________________________________________________________________
6 Authority to consider the relevance of this Clause in the context of the level of service being provided by [Sub-hubco/Project Co] and the direct costs (if any) that [Sub-hubco/Project Co] will incur as a result of a request for Additional Hours.