The Service Provider may withhold or delay consent to a novation only where the Proposed Substitute is not the Board and the Board has failed to show to the Service Provider's satisfaction (acting reasonably) that:
4.3.1 the Proposed Substitute has the legal capacity, power and authorisation to become a party to and perform the obligations of Project Co under the Service Contract; and
4.3.2 the technical competence and financial standing of and the technical and financial resources available to the Proposed Substitute are sufficient to perform the obligations of Project Co under the Service Contract.
The Service Provider shall notify the Board in writing, within [five (5)] Business Days of the later of receipt of a Proposed Novation Notice and all information required under Clause 4.2, as to whether or not it has decided to grant such consent (together with an explanation of its reasons if it has decided to withhold its consent) and, at the same time, provide a copy of the same to the Senior Funder.