1.  MONTHLY REPORT AND COMPLETION CERTIFICATION

The Independent Tester shall:

1.1  During the Works, provide the Board and Project Co with a monthly report on the activities carried out by the Independent Tester.

1.2  Undertake regular inspections during the Works, as necessary, in accordance with the [periods set out in the Completion Criteria]60. Report on the completion status of the Project, identifying any work that is not compliant with the Board's Construction Requirements, Project Co's Proposals, the Approved Reviewable Design Data (Approved RDD) and/or the Completion Criteria.

1.3  Error! AutoText entry not defined.Determine whether any relevant Phase is finished or complete in accordance with the Completion Criteria and advise Project Co and the Board of the need for any re-testing which may be necessary to demonstrate whether a relevant Phase of the Project is finished or complete.]

1.4  Certify the Actual [Phase] Completion Date and issue a Certificate of [Phase] Practical Completion in accordance with the Project Agreement.

1.5  Within [five (5)] Business Days of issue of the [relevant] Certificate of Practical Completion, issue a Snagging Notice specifying any Snagging Matters. Monitor and review rectification of such Snagging Matters in accordance with the Project Agreement.

1.6  Review the programme for the rectification of all Snagging Matters to be carried out and advise Project Co and the Board as appropriate.

And in order to enable the Independent Tester to discharge these primary functions which are to be performed independently, fairly and impartially to and as between Project Co and the Board and having regard to the interests of Funders, the Independent Tester shall discharge the further duties described below.




___________________________________________________________________________

60  Insert periods here if not included in Completion Criteria.