PROCEDURE REVIEW

The Independent Tester shall:

1.11  Monitor the operation of the quality assurance procedures of the Contractor at regular intervals (maximum [three (3)] months) during the execution of the Works.

1.12  The Independent Tester shall familiarise itself with the proposed procedures and programmes for the testing and commissioning of the [Mechanical and Electrical engineering services] prior to the Board's occupation.

1.13  Monitor the procedures for the identification, approval and recording of agreed Variations to the Works in accordance with the Project Agreement.

1.14  Review any samples or mock ups as required by Schedule [●] and check that they have been approved in accordance with the Project Agreement.