7.  RE-COMMISSIONING109

7.1  Where a Functional Part which is listed in Appendix E to this Part 18 of the Schedule (Payment Mechanism) requires Re-commissioning by or at the direction of the Board following Rectification of an Unavailability Event, the Re-commissioning of the Functional Part shall be deemed to have been completed on the earlier of:

7.1.1  the expiry of forty-eight hours after the time and date notified to the Board in the Rectification Confirmation Notice as the time and date that the Rectification was completed;

7.1.2  the time and date on which the Board or the relevant Board Party commences to use the Functional Part again for the purposes for which it was being used prior to the occurrence of the relevant Unavailability Event.

7.2  If paragraph 7.1 (Re-Commissioning) applies, an Unavailability Event shall be deemed to have occurred in respect of the affected Functional Part in each Session following Rectification up to and including the Session in which the Re-commissioning of the Functional Part shall have been deemed to have been completed.

7.3  Paragraphs 7.1 (Re-Commissioning) and 7.2 (Re-Commissioning) shall not affect the right of the Board to issue, in accordance with the Service Level Specifications, an Ad-Hoc Service Request for the provision of cleaning or other Services by Project Co in connection with any Re-commissioning activities carried out by the Board.




___________________________________________________________________________

109  Only required if activities carried out by the Board are required prior to Board use (e.g. setting of cultures to determine sterility). Likely to be required if there are e.g. theatres or sterile labs.