PART 21 OF THE SCHEDULE: INSURANCE REQUIREMENTS
>
Section 1 Policies to be taken out by Project Co and maintained during the [design and construction phase].
>
2 Delay in Start Up Insurance (DSU)
>
2.4 Minimum Indemnity Period
2.4 Minimum Indemnity Period
[12] months.