6.1 The General Procedure shall be operated in respect of Board Works Variations so that, subject to the other provisions of this Agreement providing for the adjustment of any amount payable under this Agreement, the Capital Expenditure used to assess the effect of the Qualifying Variation in respect of the Board Works Variation shall be:
(a) the proposed amount of Capital Expenditure in respect of the Board Works Variation specified in Project Co's notice under paragraph 3.2(b) of this Section 1 of Part 22 of the Schedule; or
(b) (if that sum was not agreed by the Board's Representative) the corresponding sum in respect of that Board Works Variation which was agreed by the Board's Representative and Project Co or determined in accordance with Part 26 of the Schedule (Dispute Resolution Procedure).
___________________________________________________________________________
176 See footnotes to Section 3 concerning the machinery to adjust the Service Payments.