9.1 Where there is a change to the Board Policies (subject to Clause 32.7 (Site Security and Personnel Issues) or a change of use or occupancy of, or operational hours or activities carried on within the whole or any part of the Facilities by the Board or any Board Party, either party shall be entitled to advise the other party by notice in writing that it considers that a Service Variation has arisen or will arise by operation of the change provided that it does so within three (3) months of the date when it became aware, or ought reasonably to have become aware, of the relevant change. Any notice so served shall describe in as much detail as practicable the nature of the Service Variation which is likely to be required as a result of the change and the date by which the relevant Service Variation must be implemented.
9.2 The Board (in the case of a notice under paragraph 9.1 from Project Co) or Project Co (in the case of a notice under paragraph 9.1 from the Board) shall within fifteen (15) Business Days of receipt of the notice under paragraph 9.1 set out its response to the matters set out in such notice. Any dispute as to the nature of the relevant change or as to its effect shall be referred for resolution in accordance with Part 26 of the Schedule (Dispute Resolution Procedure).
9.3 Within fifteen (15) Business Days of agreement or determination pursuant to paragraph 9.2 above that a relevant change has occurred which requires a Service Variation to be implemented, the provisions of this Section 1 shall apply to the definition and implementation of the Service Variation as if it were a Board Service Variation and as if the notice referred to in paragraph 9.1 of this Section 1 was a Board Service Variation Confirmation given at the end of such period of fifteen (15) Business Days.