Following no retendering

1.7  If the Board follows the no retendering procedure set out in paragraph 4 of Section B of this Part 23 of the Schedule then, subject to paragraph 1.8, the Board shall pay to Project Co an amount equal to the Adjusted Estimated Fair Value of the Agreement no later than the date falling twenty (20) Business Days after the Compensation Date together with interest on such amount calculated in accordance with paragraph 1.2(b) above unless the Board has paid Post Termination Service Amounts pursuant to paragraph 3.5 of Section B of this Part 23 of the Schedule.

1.8  To the extent that the Adjusted Estimated Fair Value of the Agreement is less than zero, then an amount equal to the Adjusted Estimated Fair Value of the Agreement shall be due and payable by Project Co to the Board on the Compensation Date.