6.1 The Authorities have identified the following three categories of decisions and other actions to be taken and carried out during the Procurement Milestones together with the means by which they will be taken:
6.1.1 a "Project Director Matter", being a matter which the Project Director shall have authority to carry out on behalf of the Authorities;
6.1.2 a "Project Board Matter", being a matter which it is expected that any or all of the representatives of each of the Authorities appointed pursuant to Clause 7.3 (Project Board) will be able to make a decision upon and have the power to bind the Authority it represents in doing so; and
6.1.3 a "Matter Reserved To Authority", being a matter which shall be reserved to each Authority for an executive decision under the Local Government Act 2000 as amended by the Local Government and Public Involvement in Health Act 2007 and, for the avoidance of doubt, that matter requiring a decision would not be dealt with by the representatives of the Authorities appointed pursuant to Clause 7.3 (Project Board), the Project Manager or the Lead Authority (as the case may be) until the decision shall have been taken,
and, in each case, such matters are identified in Schedule 1 (Procurement Milestones).