Authorities should note that THESE procurement milestones and associated cateogorisation ARE indicative only
MILESTONE | PROJECT | PROJECT | MATTER |
1. Procurement of external advisers to the Project | Yes |
|
|
2. Approval and confirmation of external advisers to the Project |
| Yes |
|
3. Review of the Outline Business Case to be submitted to WIDP |
| Yes |
|
4. Agreement as to recommendation for the Authorities to procure an Option and/or Site. |
| Yes |
|
5. Decision to acquire an option on or any or all of the Sites |
|
| Yes |
6. Drafting and issuing Prior Indicative Notice | Yes |
|
|
34 Preparation of the Descriptive Document and Pre Qualification Questionnaire ("PQQ") | Yes |
|
|
35 Agreeing final version of the Descriptive Document and PQQ |
| Yes |
|
36 Drafting OJEU Notice | Yes |
|
|
37 Agreeing OJEU Notice |
| Yes |
|
38 Issuing OJEU Notice | Yes |
|
|
39 Preparation of Evaluation Criteria for all stages of the procurement process | Yes |
|
|
40 Agreeing Evaluation Criteria for all stages of the procurement process |
| Yes |
|
41 Organising open days prior to return of PQQ's and Expressions of Interest | Yes |
|
|
42 Evaluation and Long-listing of Bidders | Yes |
|
|
43 Agreement of long list |
| Yes |
|
44 Inform successful and unsuccessful applicants. | Yes |
|
|
45 Drafting Invitation to Submit Outline solutions ("ISOS") | Yes |
|
|
46 Reviewing ISOS |
| Yes |
|
47 Agreeing ISOS |
|
| Yes |
48 Issue ISOS | Yes |
|
|
49 Arrange the interviews/bidder presentations | Yes |
|
|
50 Evaluation and short listing of ISOS bidders | Yes |
|
|
51 Provisional agreement to ISOS shortlist |
| Yes |
|
52 Final agreement to ISOS shortlist |
|
| Yes |
53 Drafting Invitation to Submit Detailed Solutions ("ISDS") | Yes |
|
|
54 Reviewing ISDS |
| Yes |
|
55 Agreeing ISDS |
|
| Yes |
56 Issue of ISDS | Yes |
|
|
57 Evaluation of initial responses to ISDS. | Yes |
|
|
58 Organising clarification meetings | Yes |
|
|
59 Provisional selection of Bidders to go to Final Stage | Yes |
|
|
60 Review of evaluation and selection of Bidders to go to Final Stage. |
| Yes |
|
61 Final approval of evaluation and selection bidders to go to Final Stage |
|
| Yes |
62 Evaluation of final Bids and selection of Preferred Bidder | Yes |
|
|
63 Review of final Bids and selection of Preferred Bidder |
| Yes |
|
64 Agreement to selection of Preferred Bidder |
|
| Yes |
65 Clarification and Final Close 66 Dispatch of Alcatel letters | Yes |
| Yes |
67 Agreement and execution of Project Agreement and Second Inter Authority Agreement |
|
| Yes |
68 Collation of information and provision of information in respect of Project Agreement award procedures required under Regulation 23 Public Services Contracts Regulations | Yes |
|
|
69 Approval of additional expenditure for the Project in excess of the £ million budget referred to in the Outline Business Case |
|
| Yes |
NB Gateway Reviews to be included in the Milestones.