15  Destination of assets on expiry or early termination

The Authorities will need to agree between themselves the ultimate destination and ownership of assets on expiry or earlier termination of the Project. During the Project, appropriate land arrangements can be put into place. On termination or expiry, however, continued access to the facilities should be considered and planned.  This is another area of potential complication where part of the Project could terminate early as opposed to termination of the whole Project. The Authorities will need to agree responsibility for the remediation of land after expiry, or termination of the Project Agreement.