Access following Construction

14.2  After the occurrence of the Actual Completion Date the Board shall procure the grant  of a  Licence to  Project Co and Project Co Parties of the right to enter upon the Facilities solely for the purposes of:

(a)  the carrying out of Project Operations (other than those Project Operations which Project Co is licensed to carry out pursuant to Clause 14.1); and

(b)  remedying of Defects and the carrying out of Snagging Matters; and

(c)  exercising the Ancillary Rights,

and such rights to terminate on the Expiry Date or  (if earlier) the Termination Date.