Dates for Completion

19.1  Project Co shall complete the Works by the Completion Date. Without prejudice to Clauses 44 (Project Co Events of Default), 46 (Non-Default Termination), 47(Effect of Termination) and 48 (Compensation on Termination), the Board shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date and the Actual Completion Date.41  

 




______________________________________________________________
4The standard form does not impose liquidated (i.e. pre-quantified) damages for late completion. Provisions of that nature should only be inserted if there are project specific reasons for requiring them and the Board can demonstrate that Project Co pricing this risk represents value for money (see DoH and relevant Scottish Government Health Directorates Guidance). Liability for general damages for late completion has been excluded on the same basis.