19.5 Project Co shall notify the Board's Representative if at any time the actual progress of the Works is significantly ahead of the Programme so that Project Co anticipates that the Actual Completion Date [a Phase Actual Completion Date] will be earlier than the Completion Date [relevant Phase Completion Date]. The Board's Representative shall be entitled to require Project Co to produce and submit to the Board's Representative, in accordance with Part 10 of the Schedule (Review Procedure), a revised Programme showing the manner and the periods in which the Works will be carried out and what the revised date for completion would be to enable the parties to consider (at their absolute discretion):
(a) whether to agree an earlier date for completion; and
(b) what modifications (if any) will be required to the Agreement in order to accommodate such earlier date for completion.42
______________________________________________________________
42 Provision for notification of early completion has been included to enable the parties (at their discretion) to consider early occupation by the Board of the Facilities. The consequential amendments required as a result of agreeing to that option would have to be considered and agreed on a project specific basis at the time. (For example, dealing with knock on effect on commissioning programmes, phasing, equipment procurement, payment etc).