22.  PRE-COMPLETION COMMISSIONING AND COMPLETION46

 











______________________________________________________________
46 The standard form envisages the following sequence of events:

  Final Commissioning Programme ("FCP") agreed

  Project Co commissioning needed in order to achieve Practical Completion

  Board to carry out its commissioning activities scheduled to take place prior to completion (if any)

  Project Co to carry out completion tests in accordance with FCP

  Visual inspection by Board and Independent Tester

  Certificate of Practical Completion and snagging list issued

  Commencement of appropriate percentage of the unitary charge - see Clause 35.1

  Project Co post completion commissioning activities in accordance with FCP

  Board post completion commissioning (including, for example, installation of its equipment and decant to new site) in accordance with FCP.