22.  PRE-COMPLETION COMMISSIONING AND COMPLETION46

 











______________________________________________________________
46 The standard form envisages the following sequence of events:

∙  Final Commissioning Programme ("FCP") agreed

∙  Project Co commissioning needed in order to achieve Practical Completion

∙  Board to carry out its commissioning activities scheduled to take place prior to completion (if any)

∙  Project Co to carry out completion tests in accordance with FCP

∙  Visual inspection by Board and Independent Tester

∙  Certificate of Practical Completion and snagging list issued

∙  Commencement of appropriate percentage of the unitary charge - see Clause 35.1

∙  Project Co post completion commissioning activities in accordance with FCP

∙  Board post completion commissioning (including, for example, installation of its equipment and decant to new site) in accordance with FCP.