______________________________________________________________
46 The standard form envisages the following sequence of events:
∙ Final Commissioning Programme ("FCP") agreed
∙ Project Co commissioning needed in order to achieve Practical Completion
∙ Board to carry out its commissioning activities scheduled to take place prior to completion (if any)
∙ Project Co to carry out completion tests in accordance with FCP
∙ Visual inspection by Board and Independent Tester
∙ Certificate of Practical Completion and snagging list issued
∙ Commencement of appropriate percentage of the unitary charge - see Clause 35.1
∙ Project Co post completion commissioning activities in accordance with FCP
∙ Board post completion commissioning (including, for example, installation of its equipment and decant to new site) in accordance with FCP.