22.10 Project Co shall give the Independent Tester and the Board's Representative not less than [ ] Business Days' notice and not more than [ ] Business Days' notice [the appropriate notice period for that Phase as set out in the Completion Process] of the date upon which Project Co considers that [the relevant Phase of] the Works will be complete and the tests on completion [required for the relevant Phase] to be performed in accordance with the Final Commissioning Programme will be carried out. [Following receipt of the notice specified in this Clause 22.10 the] The Board's Representative and the Independent Tester shall be entitled to inspect [the relevant Phase of] the Works on the date or dates reasonably specified by Project Co in accordance with this Clause 22.10, and to attend any of the tests on completion [undertake inspections of any Phase in accordance with the periods specified in the Completion Process]. Project Co shall, if so requested, accompany the Board's Representative and the Independent Tester on any such inspection.