As-built specification

22.17  As soon as it is available, after the issue of the Certificate of Practical Completion [in relation to a Phase to the extent relating to that Phase], Project Co shall provide to the Board a copy of the as-built building specification, together with all [drawings relating to the Works].56

 




______________________________________________________________
5To be specified on a project specific basis.  Documents might include, for example: the appropriate section of any health and safety file; as-built drawings and maintenance manuals; and results of technical commissioning.