23.5 With effect from the Commissioning End Date and throughout the remainder of the Project Term, [Within [ ] Business Days after the completion of any Phase] Project Co shall at all reasonable times make available on the Site to the Board's Representative all operation and maintenance manuals [Board to list any other manuals required].
______________________________________________________________
59 To be amended on a project specific basis. For example, operational manuals may need to be made available at an earlier date depending on the timing of commissioning activities. Furthermore, it may be possible, for Project Co to provide draft manuals to the Board for comment prior to finalisation and suitable amendments should be made to the Clause where relevant.