28.1 No later than [ ] months prior to the Completion Date Project Co shall submit to the Board's Representative in accordance with Part 10 of the Schedule (Review Procedure) a Schedule of Programmed Maintenance for the period from the Completion Date to the expiry of that Contract Year.
28.2 Not later than [ ] months prior to the commencement of each subsequent anniversary of the Completion Date [the time prescribed in [specify the relevant place to be included in Part 10 of the Schedule (Review Procedure)] Project Co shall submit to the Board's Representative in accordance with Part 10 of the Schedule (Review Procedure) a Schedule of Programmed Maintenance for the next succeeding Contract Year [for the period from the commencement of Services in respect of that Phase to the expiry of the Contract Year in which such date falls].
28.3 Each Schedule of Programmed Maintenance shall contain the following information (the "Programmed Maintenance Information"):
(a) details of the proposed start and end dates for each period of Programmed Maintenance, the works to be carried out and the proposed hours of work; and
(b) details of any effect of the Programmed Maintenance on the delivery of any of the Services and/or the activities of the Board.
28.4 Not later than [ ] Business Days prior to the commencement of any quarter (being a three month period commencing on 1 April, 1 July, 1 October or 1 January68), Project Co may submit to the Board's Representative for approval in accordance with paragraph 1.3 of Part 10 of the Schedule (Review Procedure) a revision to the Schedule of Programmed Maintenance for the Contract Year in which the relevant quarter falls showing the effect of the proposed changes to the Programmed Maintenance Information. If the Board's Representative does not raise comments on such proposed revision in accordance with Part 10 of the Schedule (Review Procedure), the Schedule of Programmed Maintenance as revised shall become the Schedule of Programmed Maintenance in respect of that quarter.
28.5 Where the Board's Representative raises comments in respect of any Programmed Maintenance periods and/or hours of work shown in a Schedule of Programmed Maintenance in accordance with paragraph 3(h) of Part 10 of the Schedule (Review Procedure), he shall indicate whether, and if so when, the Programmed Maintenance can be re-scheduled and Project Co shall amend the relevant Schedule of Programmed Maintenance accordingly.
______________________________________________________________
68 Project specific – periods may vary from project to project.