33.4 Project Co shall not install, keep or use in or on the Facilities any materials, equipment or apparatus the installation, keeping or use of which is likely to cause (or in fact causes):
(a) material damage to the Facilities;
(b) dust, noise or vibration constituting a nuisance to the owners and/or occupiers of any property adjoining or near to the Facilities; or
(c) the generation, accumulation or migration of any hazardous substance in an unlawful manner whether within or outside the Facilities,
and shall use all reasonable endeavours to ensure (by directions to staff and otherwise) that all materials, equipment or apparatus in or on the Facilities is operated so as to minimise noise and vibration likely to cause annoyance or disturbance and the unlawful generation or migration of any hazardous substance.
33.5 Save for articles or things commonly used or generated in hospitals, Project Co shall not bring in or on to (or keep or maintain in or on) the Facilities any hazardous materials or equipment without the prior written consent of the Board and unless Project Co has complied with all relevant Law.
33.6 Without prejudice to the generality of its obligations, Project Co shall:
(a) procure that all hazardous materials and equipment used or stored on the Site shall be kept in accordance with Good Industry Practice, properly and securely labelled and stored, under appropriate supervision and used only by appropriately trained and competent staff; and
(b) use all practicable and reasonable means to:
(i) prevent or counteract the unlawful emission of any hazardous substance to the satisfaction of the Board's Representative;
(ii) avoid the unlawful discharge into any conducting media serving the Facilities of any hazardous substance;
(iii) prevent the unlawful generation, accumulation or migration of any hazardous substance at or from the Facilities; and
(iv) prevent any environmental claims arising or any circumstances arising likely to result in any environmental claims,
in so far as such hazardous substance is, or should be, under the control of Project Co pursuant to this Agreement.
33.7 [Board to include project specific provisions for any sale of existing stocks and materials to Project Co.]