43.12 The parties shall endeavour to agree any modifications to the Agreement which may be equitable having regard to the nature of an event or events of Force Majeure. Part 26 of the Schedule (Dispute Resolution Procedure) shall not apply to a failure of the Board and Project Co to reach agreement pursuant to this Clause 43.12.