(c)
(i) Project Co committing a material breach of its obligations under this Agreement which has a material and adverse effect on the delivery of Clinical Services or any other services140 at the [Hospital] for which Project Co is not responsible (other than as a consequence of a breach by the Board of its obligations under this Agreement);
(ii) Project Co wilfully breaches Part 29 of the Schedule (Refinancing);
(d) Project Co abandoning the Works (other than as a consequence of a breach by the Board of its obligations under this Agreement);
(e) Project Co ceasing to provide all or a substantial part of the Services to the Board in accordance with this Agreement (other than as a consequence of a breach by the Board of its obligations under this Agreement);
______________________________________________________________
140 Boards to consider which "other services" are material to its ability to provide the Clinical Services. Consider listing specified services.