Exhibit 6.7 Key Results of Using PPPs to Deliver International Transit Projects

Exhibit 6.7 Key Results of Using PPPs to Deliver International Transit Projects

PPP Project

PPP Type

Timeframe

Cost

Economic Development

Other

Australia - Sydney Airport Transit Link

BOOT

Completed on schedule

Not available

Not available

Required A$704 million government bailout after project was placed in receivership in November 2000, six months after opening. This resulted from ridership levels of only one-quarter what was projected for the facility. The low ridership levels for the Sydney Airport Link were exacerbated by competition from another PPP project, the Eastern Distributor highway which runs parallel to the Link.

Australia - Brisbane Airport Rail Link

BOOT

Completed on schedule

Not available

Not available

Ridership far below estimates, sharply reducing credit rating for concessionaire. Government will take over the facility after 5 years of 35-year operating concession.