9.1 Ranking

Data generated from the scoring and cost modelling of the options should be collated to inform the initial ranking of options.

Table 3: Summary of Results

Options

Weighting

A

B

C

D

E

Score (%)

Full Economic Cost

Ranking

0.60

0.40

1.00

49%

£140m

Equal 3rd

76%

£100m

Equal 1st

60%

£150m

Equal 3rd

81%

£110m

Equal 1st

46%

£150m

5th

The initial ranking process may be partial For example returning to the example set out in Table 2 it can be seen that Option E is clearly the lowest ranked option as there are no other options which are more costly and it has the lowest score. It is also possible to conclude that Options B and D are both superior to both of Options A and C as they have higher scores and lower cost. The relative ranking of Options A and C is not a critical issue but the choice between Options B and D will be decisive in determining the technology for the Reference project.

Further steps are therefore required to finalise the outcome of the options appraisal.