This chart lists PPP projects in the United States that are in various stages of active procurement.
Estimated Total Project Cost in Nominal $ ($ millions) | Project Name | State | Project Sponsor and/or Owner | Proposed Project Delivery Model | Key Procurement Dates |
$2,177 | Detroit River International Crossing271 | MI | Michigan DOT / Transport Canada | DBFOM with either real tolls or availability payments | • RFPOI issued: January 2010 • Report submitted to Legislature: May 2010 |
$1,930 | First Coast Outer Beltway272 | FL | Florida DOT | Not known | • Original RFQ issued: December 2007 • Original procurement terminated: April 2008 New RFQ (planned): To be determined • RFP (planned): To be determined |
$1,680 | Midtown Tunnel/Downtown Tunnel/MLK Extension273 | VA | Virginia DOT | • Interim agreement signed: January 2010 | |
$1,500 to $2,000 | U.S. 460 Improvements274 | VA | Virginia DOT | • Original procurement initiated: 2006 • Original procurement terminated: May 2010 • New SFP issued: May 2010 | |
$1,100 | West by Northwest Managed Lanes Project, Northwest Corridor Segment275 | GA | Georgia DOT | • RFQ: February 2010 • RFQ finalists chosen: June 2010 | |
$1,000 | Goethals Bridge Replacement276 | NY, NJ VA | Port Auth. NY/NJ | DBM/F | • RFI issued: May 2010 • RFQ (planned): August 2010 • RFP (planned): Q1 2011 |
$1,000 | VA | Virginia DOT | • Interim agreement signed: October 2006 • Commercial close: Postponed indefinitely as of September 2009 | ||
$1,000 | Presidio Parkway (Doyle Drive Reconstruction)278 | CA | California DOT (Caltrans), SF County Transportation Authority | • Draft RFP issued: May 2010 | |
Not known | Ronald Reagan Parkway Extension279 | GA | Gwinnett County | • Pre-development/feasibility phase: Until 4Q 2010 | |
Not known | GA | Georgia DOT | • NOI to issue RFQ released: July 2010 • RFQ (planned): September 2010 | ||
Not known | Puerto Rico Toll Roads R-22 and PR-5281 | PR | PR PPP Auth. / R Hwys. and Trans. Auth. | 50-year concession | • RFQ issued: June 2010 |